QUOTATIONS · PROCUREMENT

Compare the delivered package, not only the unit rate.

A checklist for connecting quantities, specification, quote inclusions and site delivery arrangements in an Irish building estimate.

TrendyBuilders editorial team · Reviewed 29 November 2026 · Worked examples

Set a common enquiry basis

Before comparing quotations for an extension or refurbishment, give each supplier or contractor the same item description, quantity basis and project information. Include the relevant drawing revision and requested timing. Record assumptions and exclusions in the comparison rather than smoothing them into one unexplained total.

Check the unit being priced

A quotation may refer to an individual unit, a pack, a square metre, a cubic metre or an installed item. Convert quantities only when the product coverage and commercial unit are known. Keep a material-only comparison separate from a labour-and-material package.

For example, the block demo has a gross wall area of 10 × 3 = 30 m². Deducting 4 m² of openings leaves 26 m². A nominal 0.4 × 0.2 m face gives 325 blocks before allowance. With the selected 5% allowance, rounding up produces 342 blocks. At the illustrative EUR2.70 each, the block-unit subtotal is EUR923.40.

This excludes mortar, reinforcement, lintels, finishes, labour and delivery. It does not specify a wall system or establish structural suitability. Confirm the actual product and construction details before converting the calculation into a purchase.

Describe how the materials reach the work

  • Confirm the delivery location and the supplier’s quoted delivery basis.
  • Check vehicle access, unloading responsibility and the intended storage position.
  • Identify handling from the drop-off point to the work area.
  • Review phased deliveries against storage space and the work sequence.
  • Record validity, availability, lead-time assumptions and excluded charges.

Leave a clear decision trail

Show the quantity, quoted rate, known additions and unresolved items in adjacent lines. State whether the quotation includes or excludes tax without assuming a particular treatment. Reconfirm details with the supplier when the specification, destination or timing changes.

TB supports calculation and planning; it does not reserve stock, place the order or guarantee a delivery arrangement. Use the reviewed estimate as a basis for the next conversation, then confirm the commercial details directly.

Review a TB sample estimate

YOUR NEXT EXTENSION, REFURBISHMENT OR MATERIAL ORDER

Bring the working detail into your next estimate.

Explore construction quantities, purchasing, editable costs and resource planning in TrendyBuilders. Find a plan for your own work or your team.

Make every allowance explainable.See plans